    Default Levelling Brickwork

    Hi All,
    I'm about to build a brick retaining wall on concete footings. The footings run out about 30mm from horizontal over their length. I need to level this out in the first course of bricks. Simplest way I guess is to use the mortar bed, but this would mean it would be about 40mm thick at the lowest point, which might be too thick? On the other hand I don't want to try and shave a few mm off a load of bricks. All advice very welcome.
    Cheers, Clive.

  2. # ADS
    Google Adsense Advertisement
    Join Date
    Always
    Location
    Advertising world
    Posts
    Many





     
  3. #2
    Join Date
    Apr 2006
    Location
    melbourne
    Age
    52
    Posts
    48

    Thumbs up

    Clive

    40mm is fine, let the mortar go off a bit longer before you lay your brick, so as not to sink. How high is your retaining wall? I ask because if it is too high in ground that moves you might have to incorperate piers or go to blockwork.

  4. #3
    Join Date
    Jul 2005
    Location
    Oberon, NSW
    Age
    63
    Posts
    13,360

    Default

    There's another option, if the founds are below ground level and backfill will cover the lower courses. (I know, I know... but I've seen it done on a lot more than one occasion!)

    Run the first course with a 10-15mm fall, then make up the difference on the next. 'Tis not as pretty but brings the beds back to more reasonable/workable sizes.

    Or you could simply grind down the courses over the whole height of the wall. A few mm here, a few there. It's surprising how few people pick up on it, short of actually using a level to check.
    I may be weird, but I'm saving up to become eccentric.

    - Andy Mc

  5. #4
    Join Date
    Apr 2006
    Location
    Sydney
    Posts
    26

    Default

    Quote Originally Posted by DanM
    ...How high is your retaining wall? I ask because if it is too high in ground that moves you might have to incorperate piers or go to blockwork.
    Quote Originally Posted by Skew ChiDAMN!!
    There's another option, if the founds are below ground level and backfill will cover the lower courses. (I know, I know... but I've seen it done on a lot more than one occasion!)...
    Thanks for the help guys. The wall will be max 900mm high, sits on 650 x 350mm concrete footings in medium clay (class M). You think this will be OK? Because of the ground levels the top of the first course will be visible along most of the wall so I need it to be level by then.

  6. #5
    Join Date
    Apr 2006
    Location
    melbourne
    Age
    52
    Posts
    48

    Thumbs up

    In your street/area are there any other brick retaining walls, brick fences, brick mail boxes. Check them out, if they have crack and moved there is a good chance yours will too. 900mm high retaining soil, there is a a bit of weight there and if it is falling away from your house water will be there too, have you thought of drainage?

  7. #6
    Join Date
    Jul 2004
    Location
    Sale
    Age
    68
    Posts
    1,328

    Default

    I'm no bricklayer but 40mm sounds a bit much for a mortar bed. You could do a slate sandwich, lay run of mortar, bed a piece of slate second mortar run then first course of bricks. Never laid a brick in my life, but it is how we packed up to level stone blocks and it certainly never failed on that type of work.

    John

  8. #7
    Join Date
    Apr 2006
    Location
    Williamstown
    Posts
    40

    Default

    What about laying a new layer of concrete over the top to obtain level first?

  9. #8
    Join Date
    Apr 2006
    Location
    melbourne
    Age
    52
    Posts
    48

    Thumbs up

    No need to reinvent the wheel! 40mm is fine, bit more cement to the compo mix and dont forrow the bed and let it go off before laying the next course.

  10. #9
    Join Date
    Jun 2004
    Location
    Perth WA
    Posts
    1,764

    Default

    Quote Originally Posted by encino_
    What about laying a new layer of concrete over the top to obtain level first?
    Best choice.

    40mm may not be fine as the length of the wall is not stated.
    Squizzy

    "It is better to be ignorant and ask a stupid question than to be plain Stupid and not ask at all" {screamed by maths teacher in Year 8}

  11. #10
    Join Date
    Apr 2006
    Location
    melbourne
    Age
    52
    Posts
    48

    Thumbs up

    The lenght of the wall has nothing to do with it! if the wall is 10m long u will bed it up 40mm at the low end, if it is 100m long u will bed it up 40 mm at th low end.

  12. #11
    Join Date
    Jun 2004
    Location
    Perth WA
    Posts
    1,764

    Default

    Quote Originally Posted by DanM
    The lenght of the wall has nothing to do with it! if the wall is 10m long u will bed it up 40mm at the low end, if it is 100m long u will bed it up 40 mm at th low end.
    I was referring to trying to make the difference up with the courses. If the wall is only 2m long it wont look healthy. I only build retaining walls for a living.
    Squizzy

    "It is better to be ignorant and ask a stupid question than to be plain Stupid and not ask at all" {screamed by maths teacher in Year 8}

  13. #12
    Join Date
    Apr 2006
    Location
    melbourne
    Age
    52
    Posts
    48

    Thumbs up

    Lot of work making them up in courses, do u make any money building retaining walls.

  14. #13
    Join Date
    Apr 2006
    Location
    Sydney
    Posts
    26

    Default

    Thanks everyone. The wall will have weep holes and will be drained by 100mm ag line in blue metal - I'll backfill with rubble. I've got a wall which goes up to 1.3m high built to these specs about 5 yrs ago and no problems so far, so I'm hoping 0.9m will be OK.

    I wondered about packing with slate etc (I once demolished a wall which used fibro to level the courses - not sure this is best practice...) but if mortar alone will do the job then I'll take the easy option thanks.

    Problem with a levelling layer of concrete is that it'd have to be only a few mm thick at the high spot, and I've never had much luck with thin layers of concrete (cracking, flaking etc), even using Bondcrete etc.

    The wall will be about 8.5m long, but the high point is in the middle and the top of the first course will be visible so I'd much prefer to level it out in this course.

  15. #14
    Join Date
    Apr 2006
    Location
    Wagga Wagga
    Age
    70
    Posts
    85

    Default

    Hello Clive,
    I suppose you can do what most of the fellows are saying but as a bricklayer we would just machine cut the bricks as needed.I've probably cut hundreds of bricks,pavers etc over the years for people who just drop in on the job and ask, but I'm in a country area and it's probably different in the city.
    Terry

  16. #15
    Join Date
    Jun 2004
    Location
    Perth WA
    Posts
    1,764

    Default

    Quote Originally Posted by DanM
    Lot of work making them up in courses, do u make any money building retaining walls.
    Good Lord no....we like the pothole we live in and the dirt for breakfast is great ...
    Squizzy

    "It is better to be ignorant and ask a stupid question than to be plain Stupid and not ask at all" {screamed by maths teacher in Year 8}

Page 1 of 2 12 LastLast

Similar Threads

  1. Levelling bubble (for verticality) for brace'n'bit auger
    By TassieKiwi in forum WOODWORK - GENERAL
    Replies: 0
    Last Post: 4th October 2004, 05:52 PM
  2. Levelling Feet
    By PhilBiggs in forum WOODWORK - GENERAL
    Replies: 5
    Last Post: 21st March 2004, 03:29 PM
  3. Jig Knobs, Hand Wheels, Levelling Feet & other accessories
    By Pantherx in forum HOMEMADE TOOLS AND JIGS ETC.
    Replies: 8
    Last Post: 22nd January 2004, 11:27 PM
  4. Raising / levelling lathe bed
    By djb955 in forum WOODTURNING - GENERAL
    Replies: 6
    Last Post: 4th September 2003, 11:08 PM

Tags for this Thread

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •