    Progress 06

    Yay, another shopping spree to get some more essentials for a little more progress. Items bought were:

    1ea fibro cement top coat, 3kg (flushing villaboard and nail holes) $19.84
    3ea 89mmx19mmx1.8M DAR pine (window & door inner framing) $13.65
    3ea 42mmx11mmx1.8M DAR pine (window & door outer framing) $14.58
    3ea 89mmx19mmx2.4M DAR pine (window & door inner framing) $17.73
    4ea 42mmx11mmx2.4M DAR pine (window & door outer framing) $25.32
    2ea Liquid Nails cartridge (window & door framing) $8.90
    2ea Windsor 70mmx19mmx0.9M pine picket (portico barge board) $4.32
    4ea Windsor 70mmx19mmx1.8M pine picket (gable barge board) $15.28
    3ea Windsor 70mmx19mmx1.2M pine picket (finnials) $7.95
    5ea 20mmx8mmx2.4M Tasmanian oak square edge (inner window & door edging) $42.75
    4ea 38mmx38mmx0.4mmx2.4M zinc steel angle (Villaboard corner edging) $42.76
    4ea 75mmx75mmx2.4M zinc steel angle (gable & portico flashing) $81.36
    2ea 200mmx200mmx2.4M 3 bend zinc steel ridge capping $63.85

    Step 7 - Roof Flashing

    At this point I trimmed the excess of the ends of the roof flush with the roof panels. I then pre-painted the ridge capping and some of the timber and affixed it to the main gable.

    Step 7 - Roof Flashing 01.jpg

    Next was to trim the excess Viallaboard from the face of the gables. After this was done I cut and set the larger angle flashing, cut the barge boards (pickets) to length, then nailed them into place. I also cut a section of Villaboard for the portico face.

    Step 7 - Roof Flashing 02.jpgStep 7 - Roof Flashing 03.jpg

    Next was to trim the portico capping to size and I then screwed it down. At this point I glued a piece of leftover angle against the front wall above the portico to assist as a water drip point as seen in the image below.

    Step 7 - Roof Flashing 04.jpg

    I then cut the flashing and barge boards for the portico and screwed and nailed them into place as well.

    Step 7 - Roof Flashing 05.jpg

    I had some leftover 20mm angle from a previous job, and I used this to neaten the edging where I trimmed the edge of the sheets down.

    Step 7 - Roof Flashing 06.jpg

    Step 8 - Villaboard Preparation

    I used the compound to fill in all of the nail holes in the villaboard when I affixed it to the framework. I also used the fibretape in the joints and set an initial flush. After sanding everything back I reflushed and filled for the second time.

    Step 8 - Villaboard Initial Preparation 01.jpgStep 8 - Villaboard Initial Preparation 02.jpg

    I also used the Liquid Nails to affix the corner flashing to the edges of the Villaboard. I used some aluminium tape to hold the strips in place while the glue set.

    Step 8 - Villaboard Initial Preparation 03.jpg

    Step 9 - Door & Window Framing Part 1

    I used the DAR pine for this because it does not contain any knots or defects to it's the best to use for framing. Just follow the images below to see the stages as I made the door framework.

    Step 9 - Framing 01.jpgStep 9 - Framing 02.jpgStep 9 - Framing 03.jpgStep 9 - Framing 04.jpgStep 9 - Framing 05.jpg

    So basically, top outer - top inner - bottom inner - one side inner - same side outer (repeat other side) - bottom outer.

    I was able to complete one window before the effects of the cyclone up North started to hit me with rain so I had to pack the power tools up. The next image shows the bottom left hand corner of the completed window frame.

    Step 9 - Framing 06.jpg

    I was still able to start the filling of the timber gaps and nail holes while the rain was coming and going so the last half of today of the weekend was spent just patching/flushing and sanding.

    Step 10 - Villaboard Finishing 01.jpgStep 10 - Villaboard Finishing 02.jpgStep 10 - Villaboard Finishing 03.jpg

    Cost to date: $1492.09.

  2. # ADS
    Google Adsense Advertisement
    Join Date
    Always
    Location
    Advertising world
    Age
    2010
    Posts
    Many





     
  3. #17
    Join Date
    Feb 2013
    Location
    perth western australia
    Posts
    1

    Default

    That is looking awesome mate

Page 2 of 2 FirstFirst 12

Similar Threads

  1. WIP Pics - Playground Cubby
    By gib802 in forum WOODWORK PICS
    Replies: 14
    Last Post: 2nd January 2012, 11:01 AM
  2. Cubby House
    By wheelinround in forum HAVE YOUR SAY
    Replies: 5
    Last Post: 21st May 2010, 05:26 PM
  3. Cubby house
    By Wongo in forum WOODWORK PICS
    Replies: 41
    Last Post: 6th August 2009, 01:46 PM
  4. Cubby House WIP
    By echnidna in forum WOODWORK - GENERAL
    Replies: 10
    Last Post: 31st October 2007, 01:45 AM

Tags for this Thread

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •