    Question Deck building process

    Hello All,

    Like a lot of people using this site I am a novice an building decks but have general renovation experience.

    I am building a full jarrah deck 5.5 x 6.5m about 300mm off the ground. I have used design guides to determine the correct spacing and sizing of timber bearers and joists.

    The question I have is in regard to the process for construction and specifically installing the posts.

    I figure there are 2 options:
    • install each post individually (using wet mix concrete) getting levels correct and ensuring the post is vertical, or
    • join bearer to posts (average of 4 posts per bearer) and slot into post holes, prop and level and then pour concrete into all holes at once.
    Any suggestions would be greatly appreciated. Also what depth should the posts go into the ground? I have read 300mm, 400mm and 500mm in different publications!

    Regards, Almost Novice.

  2. # ADS
    Google Adsense Advertisement
    Join Date
    Always
    Location
    Advertising world
    Posts
    Many





     
  3. #2
    Join Date
    Jan 2005
    Location
    Canberra
    Posts
    265

    Default

    Quote Originally Posted by almost novice
    join bearer to posts (average of 4 posts per bearer) and slot into post holes, prop and level and then pour concrete into all holes at once.
    you're only 300 off the ground so option 2 would probably be easier for you, run a few joists across aswell to tie it all together.

    what soil type do you have, 300 would be ok for the concrete stuff we have here (clay) but go deeper for sandier soils.

  4. #3
    Join Date
    Jun 2003
    Location
    brisbane
    Posts
    253

    Default

    I agree with the pope (not the one in rome) just make sure you prop the posts so that the post stirrup isn't sitting on the bottom of the hole.

  5. #4
    Join Date
    Jun 2004
    Location
    Canberra
    Age
    45
    Posts
    452

    Default

    Just finished my deck and went with option Two. Worked well, and as said just make sure the stirrups protrude from the hole the correct distance.
    I want to die peacefully in my sleep like my grandfather, not screaming in terror like the passengers in his car.

  6. #5
    Join Date
    Mar 2006
    Location
    Adelaide
    Posts
    2

    Default

    Thanks for the advice. Looks like option 2 has the thumbs up.

    At this stage I'm using long posts and going straight into the ground and pouring the concrete around the posts. I think that the key issue here is ensuring that the concrete is well rodded at the bottom to ensure that the concrete goes completely under the bottom of the posts.

    This option also provides additional rigidity to the deck and the life of the jarrah posts in concrete should be ample.

Similar Threads

  1. Help with building a deck
    By captainmorgan in forum TIMBER
    Replies: 16
    Last Post: 1st December 2005, 10:04 AM
  2. Deck Building: Piles Question?
    By lisac in forum WOODWORK - GENERAL
    Replies: 11
    Last Post: 24th February 2005, 06:17 PM
  3. best for aged deck timber
    By marineman in forum TIMBER
    Replies: 6
    Last Post: 10th January 2005, 08:25 AM
  4. Replies: 11
    Last Post: 22nd November 2004, 01:48 PM

Tags for this Thread

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •