    Hi there,

    I've been trying to figure out the order in which to renovate my en suite, but just a little unclear about a few things. Here's my proposed method.

    1) Remove existing stuff (almost done)
    Attachment 56948

    - How much of the old surface needs to be cleaned/removed before tiling or waterproofing can take place?
    I have used a paint scraper and hammer to chisel off as much of the old thinset as possible. Will this surface be enough to tile back over?

    - Do i need to clean off all of the mortar from under the old shower pan?
    I can get most of it off with a bolster/hammer & crow bar, but the surface isn't "clean". Does it need to be completely clean before waterproofing?

    2) That strange hole.
    When removing the old fibreglass showerpan, i found that square hole in the slab (see picture).
    - What is that hole for?
    I assume i need to raise the waste pipe, and fill that hole with concrete, level to the rest of the slab.

    3) Walls
    - I tore down the shower walls which had tiles on them, and need to install new ones.
    - What type of sheeting/wall is recommended for use in a shower?
    - Should i leave a gap at the bottom between the slab and the bottom of the sheet?
    - I will likely get a plasterer in to fix up the trickier bits (cornering, joins, etc)

    4) Hebel block for shower curb
    - I've been told this is what's used for shower curb, and that i can cut it to size and liquid nails it to the cement.?

    5) Waterproofing
    - I plan on getting a professional waterproofer in to do this, just need to make sure the surface is ready for him/her. (see 1)
    - Does the waterproofing go directly onto the slab and around the curb/walls??

    6) Tiling..
    - Getting a professional tiler to do this.
    - Does the tiler pack a base on top of the waterproofing, then tile straight onto that?

    Thanks soo much for the advice.

    Scotte.

  2. # ADS
    Google Adsense Advertisement
    Join Date
    Always
    Location
    Advertising world
    Posts
    Many





     
  3. #2
    Join Date
    Aug 2007
    Location
    Noosa Heads
    Posts
    549

    Default

    OWW Hopoz - too many questions!! And most of the answers can be found in similiar threads.

    Basically get the existing floor and floor and walls as smooth as possible - angle grind if necessary. Remove any loose or torn waterproof membrane.

    The square hole in the floor was to fit the outlet under the old shower base - most prefab showerbases need a cut out hole in the floor. It can be filled level but get the waste pipe extended first.

    Reline walls with Villaboard - leave a 6 - 10 mm gap between boards and floor - fill with polyurethane sealant - make a nice clean line - use tape.

    Hebel block is good - use landscape grade Liquid nails or special hebel glue. There are a mob of granite bench top ppl here on sun coast that will shape a hebel slab to the exact size and ramping for a shower base for $200 complete with hob - tilers love it so easy peasy! Might be someone near you that will do it - or do it yourself if you feel artistic.

    The waterproofer will cover everything that needs waterproofing - which is probaly everywhere, and the tiler will put his scree down and tile on top



    easy!
    Last edited by Dirty Doogie; 2nd October 2007 at 12:18 PM. Reason: ??